MigrationsStar Cement S/4HANA Brownfield Migration
Phase Progression
Started: 1/15/2026 | Target Cutover: 7/30/2026
Initiation
Jan 15
Design
Feb 1
Realization
Mar 5
Test Prep
May 15
Cutover
Jul 25
Hypercare
Jul 30
Closed
Aug 30
BP Coverage
73%
+3%
SI Items Closed
68%
+5%
ABAP Findings Closed
45%
+8%
Regression Pass Rate
94.2%
+1.2%
Test Healing Rate
87%
+2%
Open Critical Defects
3
-2
Cutover Readiness
62%
+5%
Days to Cutover
84
Test Pack Coverage
89%
+2%
Active Suites Today
4
Healed Cases (7d)
12
+4
Defect Resolution (days)
3.2
-0.5
SI/ABAP Burndown & Pass Rate Trend
Last 30 days
Burndown & Trend Charts
SI Items: 96 → 31 remaining
ABAP: 503 → 276 remaining
Initiated Cutover Validation Suite execution
P.Sharma · 09:00 AM
Cutover step T0 - Lock Down ECC started
R.Kumar · 05:45 AM
Approved Pre-Cutover Gate transition
S.Mehta · 03:30 AM
Pre-Cutover Validation Suite completed with 100% pass rate
J.Rao · 11:15 AM
Defect DEF-456 resolved - ATP calculation fix
M.Reddy · 08:50 AM
SI Item SAP_NOTE_2622437 moved to In_Remediation
S.Kumar · 05:00 AM
ABAP finding Z_PRICING_CALC remediation started
M.Reddy · 11:30 AM
BP Violation BD3 accepted as deliberate deviation
R.Kumar · 09:00 AM