Phases View
Migration phases timeline with gate criteria evaluation
Timeline Overview
Initiation
Design
Realization
Test Prep
Cutover
Hypercare
Closed
1/15/20267/30/2026
Initiation
CompletedStandardPlanned: 1/15/2026 - 2/1/2026| Actual: 1/15/2026 - 2/1/2026
Design
CompletedStandardPlanned: 2/1/2026 - 3/1/2026| Actual: 2/1/2026 - 3/5/2026
3
Realization
In ProgressPre-CutoverPlanned: 3/5/2026 - 5/15/2026| Actual: 3/5/2026
Gate Criteria
BP Coverage
73% >= 80%
SI Items Closed
68% >= 60%
ABAP Findings Closed
45% >= 40%
Regression Pass Rate
94.2% >= 90%
Cannot transition
BP Coverage 73% below threshold 80%
4
Test Prep
PendingPre-CutoverPlanned: 5/15/2026 - 6/15/2026
5
Cutover
PendingCutoverPlanned: 7/25/2026 - 7/30/2026
6
Hypercare
PendingHypercarePlanned: 7/30/2026 - 8/30/2026
7
Closed
PendingStandardPlanned: 8/30/2026 - 9/15/2026