MigrationsVertex Industries S/4HANA Greenfield Rollout
MIG-VERTEX-2026Test Prep32 days to cutover

Vertex Industries S/4HANA Greenfield Rollout

Phase Progression

Started: 11/1/2025 | Target Cutover: 6/8/2026
Initiation
Nov 1
Design
Nov 15
Realization
Jan 20
Test Prep
Apr 5
Cutover
Jun 1
Hypercare
Jun 8
Closed
Jul 8
BP Coverage
91%
+3%
SI Items Closed
95%
+5%
ABAP Findings Closed
88%
+8%
Regression Pass Rate
97.5%
+1.2%
Test Healing Rate
92%
+2%
Open Critical Defects
1
-2
Cutover Readiness
85%
+5%
Days to Cutover
32
Test Pack Coverage
96%
+2%
Active Suites Today
6
Healed Cases (7d)
8
+4
Defect Resolution (days)
2.1
-0.5
SI/ABAP Burndown & Pass Rate Trend
Last 30 days

Burndown & Trend Charts

SI Items: 96 → 31 remaining

ABAP: 503 → 276 remaining

Latest Activity

Initiated Cutover Validation Suite execution

P.Sharma · 09:00 AM

Cutover step T0 - Lock Down ECC started

R.Kumar · 05:45 AM

Approved Pre-Cutover Gate transition

S.Mehta · 03:30 AM

Pre-Cutover Validation Suite completed with 100% pass rate

J.Rao · 11:15 AM

Defect DEF-456 resolved - ATP calculation fix

M.Reddy · 08:50 AM

SI Item SAP_NOTE_2622437 moved to In_Remediation

S.Kumar · 05:00 AM

ABAP finding Z_PRICING_CALC remediation started

M.Reddy · 11:30 AM

BP Violation BD3 accepted as deliberate deviation

R.Kumar · 09:00 AM