MigrationsNorthwind Manufacturing ECC Upgrade
MIG-NWIND-2026Cutover3 days to cutover

Northwind Manufacturing ECC Upgrade

Phase Progression

Started: 12/1/2025 | Target Cutover: 5/10/2026
Initiation
Dec 1
Design
Dec 15
Realization
Jan 15
Test Prep
Mar 15
Cutover
May 7
Hypercare
May 10
Closed
Jun 10
BP Coverage
98%
+3%
SI Items Closed
100%
+5%
ABAP Findings Closed
97%
+8%
Regression Pass Rate
99.1%
+1.2%
Test Healing Rate
95%
+2%
Open Critical Defects
0
-2
Cutover Readiness
98%
+5%
Days to Cutover
3
Test Pack Coverage
100%
+2%
Active Suites Today
2
Healed Cases (7d)
3
+4
Defect Resolution (days)
1.5
-0.5
SI/ABAP Burndown & Pass Rate Trend
Last 30 days

Burndown & Trend Charts

SI Items: 96 → 31 remaining

ABAP: 503 → 276 remaining

Latest Activity

Initiated Cutover Validation Suite execution

P.Sharma · 09:00 AM

Cutover step T0 - Lock Down ECC started

R.Kumar · 05:45 AM

Approved Pre-Cutover Gate transition

S.Mehta · 03:30 AM

Pre-Cutover Validation Suite completed with 100% pass rate

J.Rao · 11:15 AM

Defect DEF-456 resolved - ATP calculation fix

M.Reddy · 08:50 AM

SI Item SAP_NOTE_2622437 moved to In_Remediation

S.Kumar · 05:00 AM

ABAP finding Z_PRICING_CALC remediation started

M.Reddy · 11:30 AM

BP Violation BD3 accepted as deliberate deviation

R.Kumar · 09:00 AM